progress in the first half of 2024

Share on:

In this first half of this year, we have managed to execute the structure of the building in more than 50% of the total floors to be built.

We are on level 14 of the slabs and 17 of the main core.

In addition, the assembly of the glass façade began: at the moment two complete floors of the tower shaft have been installed.

In the interiors, the installations of the different subcontracts are being carried out on the basement and lower levels of the tower.

For the second part of the year we aim to complete the structure and begin assembling the ventilated facade of the tower’s base.